Manitoba Hydro – Preliminary Estimate Reviews
- Feb 25, 2025 Start date
- Closed Status
- None Intervenors
- None Presenters
- None Next hearing
- Application filed Feb 25, 2025 Completed
- Closed Pending In progress
Off air
Public Utilities Board reviews of Manitoba Hydro preliminary estimates; 2025: Dispatchable Capacity Resource (Board comments and recommendations issued March 2025).
Application
| Title | Type | ||
|---|---|---|---|
| MH letter to PUB dated February 25, 2025 – Manitoba Hydro Preliminary Estimate for Dispatchable Capacity Resource | Feb 25, 2025 | Application |
Information Requests
| Title | Type | ||
|---|---|---|---|
| PUB-MH I 1-11 – Responses received March 13, 2025 | Mar 13, 2025 | Information Requests |
Report
| Title | Type | ||
|---|---|---|---|
| Public Utilities Board Comments and Recommendations on Manitoba Hydro’s Preliminary Estimate for a 500 MW Dispatchable Capacity Resource – March 28, 2025 | Mar 28, 2025 | Report |